Ashton Moss Site Underway

Works have recommenced at the Ashton Moss site. The EPC Civil Engineering site team are working towards their 1st concrete foundation pour of a cumulative of 5 pours. Measuring in at approximately 300m3 per pour, EPC Civil engineering anticipate a pour every 7 days.

Status - Steel fixing, Formwork and backfilling are on schedule.

EPC Civil Engineering’s Site Manager Sylvester Grogan is keeping a firm eye on Health and safety along with the day-to-day operations on site.