Progress at Ashton continues...

73.6T steel

762m pecafil/shuttering

Triple lift pit

1017m3 pumped concrete

Ground floor slab prep 50%

External drainage


All in 2.5 weeks. Massive effort by the lads on site. Time to install the tanks and form the car parks. Can’t be achieved without an excellent team!!